Another Oil Sands Project Runs Over Budget

Suncor Energy Inc. (TSX:SU)(NYSE:SU) and Teck Resources Ltd. (TSX:TECK.B)(NYSE:TECK) increased the cost estimate for Fort Hills by 10%.

| More on:
The Motley Fool

Producers in Canada’s oil sands have encountered a range of issues over the years that have hampered the region’s ability to grow. One of the biggest issues has been cost overruns, which have crimped returns and forced producers to defer investments on other projects until they can figure out ways to drive down costs. Even the industry’s devastating downturn over the past few years hasn’t seemed to fix the problem. That’s clear after Suncor Energy Inc. (TSX:SU)(NYSE:SU) ratcheted up the cost estimate for its Fort Hills project.

Bumping up the budget

Suncor initially expected that Fort Hills, which it’s building with French oil giant Total and Canadian miner Teck Resources Ltd. (TSX:TECK.B)(NYSE:TECK), would cost $15.1 billion. Suncor also anticipated that the project would deliver first oil later this year and produce 180,000 barrels per day once it reached full capacity. However, Suncor recently said that the project would now cost between $16.5 billion and $17 billion.

An issue driving the increase was last year’s forest fires in the region, which delayed construction. However, the company also changed the complexity and scale of the project, which will add to the cost. One of the biggest changes is an increase in its production capacity to 194,000 barrels per day. Because of that expansion, the company’s cost per flowing barrel will remain around its original estimate of $84,000. Further, the project remains on track to deliver first oil later this year.

That’s good news and bad news for Suncor and its partners. In Teck Resources’s case, it had to record an after-tax impairment charge of $164 million relating to the cost increase. Further, it will need to raise its capex budget this year to fund the additional capital to bring this project to completion. That said, Teck will benefit from the project’s larger production capacity, especially if oil prices rebound sharply.

We’ve seen this all before

Suncor had initially hoped that the downturn in the oil market would keep a lid on construction costs, enabling it to avoid the cost overruns that have plagued its peers in recent years. The poster child for the industry’s problems was the Kearl oil sands mine by Imperial Oil Limited (TSX:IMO)(NYSE:IMO).

When Imperial first proposed the project in 2009, it expected the facility would cost $7.9 billion. However, it ratcheted up that price tag to $10.9 billion two years later due to changes in the scope and design. It then tacked on another $2 billion to the budget in 2013 after facing issues transporting the Korean-made modules to its mine site as well as the extra costs associated with setting it up during harsh winter conditions.

Making matters worse, it took the company more than a year to work out the kinks in the project after completion; output initially ran well below nameplate capacity due to a variety of issues, such as installation-related defects on some of the valves.

Costs had gotten out of control industry-wide before oil prices collapsed. According to a study by E&Y, 58% of large energy projects in North America ran ahead of budget by an average of 51%. Because of this, several producers decided it was better to defer new projects until the industry could get cost under control rather than risk wasting capital on a high-cost project; the oil sands were a prime target of budget cuts.

For example, Fort Hills partners Total and Suncor stopped working on their $11 billion Joslyn project well before oil prices started to collapse in 2014. Total laid off 150 employees that had been working on the project, which it said had unappealing economics, even though oil was in the triple digits at that time.

Meanwhile, Norway’s Statoil stopped working on its multi-billion-dollar Corner project, and it recently decided to unload its oil sands assets in a deal that resulted in it recording a half-billion-dollar write-down of its investment in the region because it did not see a way forward. Royal Dutch Shell halted work on its Pierre River project due to rising costs and poor economics.

Given where oil prices are these days and the fact that costs haven’t come down, it doesn’t appear that any of these projects will get a green light anytime soon.

Investor takeaway

The oil sands were once a hotbed of activity after producers swooped in to get a piece of the pie. The ensuing spending boom resulted in costs escalating out of control, forcing many to reevaluate and abandon growth plans.

Unfortunately, like Suncor’s recent announcement shows, the oil market downturn hasn’t drained costs out of the region, which is why it could still be quite some time before producers start working on any of their long-delayed mega-projects.

This article represents the opinion of the writer, who may disagree with the “official” recommendation position of a Motley Fool premium service or advisor. We’re Motley! Questioning an investing thesis — even one of our own — helps us all think critically about investing and make decisions that help us become smarter, happier, and richer, so we sometimes publish articles that may not be in line with recommendations, rankings or other content.

Fool contributor Matt DiLallo has no position in any stocks mentioned.

More on Energy Stocks

bulb idea thinking
Energy Stocks

Should Investors Buy the Correction in Cameco Stock?

Cameco stock (TSX:CCO) is up 71% in the last year, but has come back 10% in the last month. But…

Read more »

Group of industrial workers in a refinery - oil processing equipment and machinery
Energy Stocks

2 Top Energy Stocks (With Dividends) to Buy Today and Hold Forever

Besides their solid growth prospects, these two Canadian energy stocks also reward investors with attractive dividends.

Read more »

Dice engraved with the words buy and sell
Energy Stocks

Suncor Energy Stock Has Surged 25% in Just 75 Days: Is It Still a Buy?

Suncor stock has surged 25% to above $53 in the last 75 days. Is there more upside or correction for…

Read more »

Businessmen teamwork brainstorming meeting.
Energy Stocks

Cenovus Stock Is Rising, but I’m Worried About This One Thing

Cenovus Energy (TSX:CVE) stock has been one of the best performers on the TSX this year, but I do have…

Read more »

Gas pipelines
Energy Stocks

3 Reasons to Buy Enbridge Stock Like There’s No Tomorrow

Enbridge (TSX:ENB) stock has barely moved in the last few years, with ongoing issues. But there are still reasons that…

Read more »

Super sized rock trucks take a load of platinum rich rock into the crusher.
Energy Stocks

Cameco Stock and More: 3 TSX Commodity Titans to Watch in 2024

Cameco stock (TSX:CCO) has seen its share price surge this year, but there are also other commodity stocks I would…

Read more »

A worker overlooks an oil refinery plant.
Energy Stocks

Is Now the Time to Buy Suncor Stock?

Dividend stocks like Suncor Energy Inc (TSX:SU) pay a lot of dividend income.

Read more »

Gold bullion on a chart
Energy Stocks

Have $500? 2 Absurdly Cheap Stocks Long-Term Investors Should Buy Right Now

Torex Gold Resources (TSX:TXG) stock and one undervalued TSX energy stock could rise as identified scenarios play out.

Read more »