Is This Pipeline Project in Jeopardy?

Kinder Morgan’s Trans Mountain pipeline expansion has been pushed back yet again.

| More on:
The Motley Fool

Last week, Canada’s National Energy Board said that it was delaying a decision on the Trans Mountain oil sands pipeline expansion project by seven months. The project, which is proposed by Kinder Morgan’s (NYSE: KMI) master limited partnership Kinder Morgan Energy Partners (NYSE: KMP), continues to face delays and opposition. Under the revised schedule, the pipeline won’t be in service until early 2018, and that is if the expansion project does finally get approved.

The latest delay

Kinder Morgan is literally down to the last few miles on the project. In fact, the current roadblock involves the final five kilometers of the line, which would be in a heavy urban area. Those last five kilometers would take the pipeline from Burnaby Mountain, which is where Kinder Morgan Energy Partners’ tank farm is located, down to the docks where the oil can then be transported by boat.

Kinder Morgan Energy Partners has explored multiple alternative routes for the pipeline to accommodate local concerns. While the company believes that its current proposed route is the optimal placement of the pipeline, the National Energy Board wants it to take the next six months to really evaluate all of its options.

Kinder Morgan’s concern is that this will continue to drag out. The company is facing intense opposition to the project on a local level and is having a tough time getting local co-operation. That’s why the company is now asking Canadian regulators to intervene so that it can expedite the completion of these feasibility studies. In a recent report by Bloomberg, the president of Kinder Morgan Canada, Ian Anderson, stated that the city of Burnaby has terminated “virtually all communication” so that the company can’t work with the city to address the issues and concerns it has with the project.

Tough mountain to climb

Kinder Morgan’s proposed expansion project was once viewed by the industry as an easy project to be approved. The current Trans Mountain pipeline system has been in operation since 1953 and is the only existing crude oil pipeline connecting the oil sands region to the west coast. It was thought that it would be easier to approve an expansion of this already-existing system than to have a new system built. However, delays in the project have now opened up the doors for a competing project.

Enbridge (TSX: ENB)(NYSE: ENB) is slowly making its own uphill climb to see its Northern Gateway project built. Earlier this year the federal government approved the $7.9 billion project. However, it must first satisfy 209 conditions. Enbridge faces much of the same opposition as Kinder Morgan has, as both environmentalists and Aboriginal groups are opposed to the currently proposed project. The concern is that an oil spill would have a massive impact on both the environment and the livelihood of those living along the pipeline’s path.

What’s next for Kinder Morgan?

Kinder Morgan’s Trans Mountain expansion and Enbridge’s Northern Gateway pipeline are critical projects for the companies, their customers, and Canada. If these projects don’t get built it will impact the growth of both companies, as well as the growth of production from the oil sands. Furthermore, it will impact Canada’s economy as the oil sands are a big economic engine.

That’s why I think Kinder Morgan will eventually build its $5.6 billion pipeline; however, it needs to ensure that it won’t cause environmental damage. To do that, it needs to take the time to make sure it does have the best possible pipeline route, as well as adequate safeguards in place to prevent a disaster. Hopefully, the extended deadline will do just that as all stakeholders can work together to put together a solution that will be acceptable to all parties.

Fool contributor Matt DiLallo has the following options: short January 2016 $32.5 puts on Kinder Morgan and long January 2016 $32.5 calls on Kinder Morgan. The Motley Fool owns shares of Kinder Morgan.

More on Investing

man in bowtie poses with abacus
Energy Stocks

The $109,000 TFSA Milestone: How Do You Stack Up?

Hitting the $109,000 TFSA milestone isn’t about perfection, it’s about building consistent habits that make tax-free income possible.

Read more »

Retirees sip their morning coffee outside.
Dividend Stocks

Retiring? $1 Million Isn’t Enough Anymore

$1,000,000 invested in iShares S&P/TSX 60 Index Fund (TSX:XIU) doesn't provide enough income to retire on.

Read more »

chart reflected in eyeglass lenses
Stocks for Beginners

3 TSX Stocks to Buy if You Think the TSX Stays Resilient

These three TSX stocks mix steady demand and growth potential across insurance, healthcare, and energy services.

Read more »

dividends grow over time
Dividend Stocks

Got $10,000? This Dividend Stock Could Deliver $44.26 a Month in Passive Income

You can turn $10K into an easy $44.26/month passive-income stream with this rock-solid Canadian REIT that's raised its payout for…

Read more »

warehouse worker takes inventory in storage room
Tech Stocks

3 Stocks I Loaded Up on Last Year for Long-Term Wealth

Understand the impact of recent geopolitical shifts on stocks and how they may influence future markets and generate wealth for…

Read more »

financial chart graphs and oil pumps on a field
Energy Stocks

3 Canadian Energy Stocks Heating Up for a Big Year

Do you want some exposure to energy stocks while oil is trading over $100 per barrel? These three stocks provide…

Read more »

investor looks at volatility chart
Metals and Mining Stocks

Gold, Staples, or Cash: Where Should You Put Your Money When Markets Get Rocky?

Long-term success comes from staying diversified and investing through market weakness.

Read more »

Printing canadian dollar bills on a print machine
Dividend Stocks

Transform Your TFSA Into a Cash-Creating Machine With $10,000

These two monthly dividend stocks can deliver stable, reliable passive income.

Read more »