Another Oil Sands Project Runs Over Budget

Suncor Energy Inc. (TSX:SU)(NYSE:SU) and Teck Resources Ltd. (TSX:TECK.B)(NYSE:TECK) increased the cost estimate for Fort Hills by 10%.

| More on:
The Motley Fool

Producers in Canada’s oil sands have encountered a range of issues over the years that have hampered the region’s ability to grow. One of the biggest issues has been cost overruns, which have crimped returns and forced producers to defer investments on other projects until they can figure out ways to drive down costs. Even the industry’s devastating downturn over the past few years hasn’t seemed to fix the problem. That’s clear after Suncor Energy Inc. (TSX:SU)(NYSE:SU) ratcheted up the cost estimate for its Fort Hills project.

Bumping up the budget

Suncor initially expected that Fort Hills, which it’s building with French oil giant Total and Canadian miner Teck Resources Ltd. (TSX:TECK.B)(NYSE:TECK), would cost $15.1 billion. Suncor also anticipated that the project would deliver first oil later this year and produce 180,000 barrels per day once it reached full capacity. However, Suncor recently said that the project would now cost between $16.5 billion and $17 billion.

An issue driving the increase was last year’s forest fires in the region, which delayed construction. However, the company also changed the complexity and scale of the project, which will add to the cost. One of the biggest changes is an increase in its production capacity to 194,000 barrels per day. Because of that expansion, the company’s cost per flowing barrel will remain around its original estimate of $84,000. Further, the project remains on track to deliver first oil later this year.

That’s good news and bad news for Suncor and its partners. In Teck Resources’s case, it had to record an after-tax impairment charge of $164 million relating to the cost increase. Further, it will need to raise its capex budget this year to fund the additional capital to bring this project to completion. That said, Teck will benefit from the project’s larger production capacity, especially if oil prices rebound sharply.

We’ve seen this all before

Suncor had initially hoped that the downturn in the oil market would keep a lid on construction costs, enabling it to avoid the cost overruns that have plagued its peers in recent years. The poster child for the industry’s problems was the Kearl oil sands mine by Imperial Oil Limited (TSX:IMO)(NYSE:IMO).

When Imperial first proposed the project in 2009, it expected the facility would cost $7.9 billion. However, it ratcheted up that price tag to $10.9 billion two years later due to changes in the scope and design. It then tacked on another $2 billion to the budget in 2013 after facing issues transporting the Korean-made modules to its mine site as well as the extra costs associated with setting it up during harsh winter conditions.

Making matters worse, it took the company more than a year to work out the kinks in the project after completion; output initially ran well below nameplate capacity due to a variety of issues, such as installation-related defects on some of the valves.

Costs had gotten out of control industry-wide before oil prices collapsed. According to a study by E&Y, 58% of large energy projects in North America ran ahead of budget by an average of 51%. Because of this, several producers decided it was better to defer new projects until the industry could get cost under control rather than risk wasting capital on a high-cost project; the oil sands were a prime target of budget cuts.

For example, Fort Hills partners Total and Suncor stopped working on their $11 billion Joslyn project well before oil prices started to collapse in 2014. Total laid off 150 employees that had been working on the project, which it said had unappealing economics, even though oil was in the triple digits at that time.

Meanwhile, Norway’s Statoil stopped working on its multi-billion-dollar Corner project, and it recently decided to unload its oil sands assets in a deal that resulted in it recording a half-billion-dollar write-down of its investment in the region because it did not see a way forward. Royal Dutch Shell halted work on its Pierre River project due to rising costs and poor economics.

Given where oil prices are these days and the fact that costs haven’t come down, it doesn’t appear that any of these projects will get a green light anytime soon.

Investor takeaway

The oil sands were once a hotbed of activity after producers swooped in to get a piece of the pie. The ensuing spending boom resulted in costs escalating out of control, forcing many to reevaluate and abandon growth plans.

Unfortunately, like Suncor’s recent announcement shows, the oil market downturn hasn’t drained costs out of the region, which is why it could still be quite some time before producers start working on any of their long-delayed mega-projects.

Fool contributor Matt DiLallo has no position in any stocks mentioned.

More on Energy Stocks

The sun sets behind a power source
Energy Stocks

This Canadian Dividend Stock Is Down 6%: I’m Holding Forever

Fortis (TSX:FTS) stock stands tall at a time like this, when investors are getting overly bullish.

Read more »

electrical cord plugs into wall socket for more energy
Energy Stocks

Canada’s AI Boom Needs Far More Electricity: These TSX Stocks Could Provide It

Canada’s AI boom may hinge on electricity supply, and two TSX power producers offer very different risk-reward paths.

Read more »

Hand Protecting Senior Couple
Energy Stocks

How Much Do You Actually Need in a TFSA to Retire?

There is no magic TFSA number for retirement, but it’s hands-down the best tool if you're playing catch-up on your…

Read more »

Colored pins on calendar showing a month
Dividend Stocks

Here’s a 4.4% Dividend Stock That Pays You Monthly

A top-performing, high-yield stock paying monthly dividends is a lower-risk income play in the unique market environment of 2026

Read more »

woman holding steering wheel is nervous about the future
Energy Stocks

Are You Behind? Here’s What Canadians Near 60 Have Saved

Canadians near 60 haven’t saved that much but are well-positioned to fortify their nest eggs in the high earning years…

Read more »

investor schemes to buy stocks before market notices them
Energy Stocks

CNQ or Enbridge? Here’s the Better Dividend Stock Right Now

Enbridge stock offers a 5.4% yield, but Canadian Natural Resources (TSX:CNQ) stock brings a cheaper valuation and faster dividend growth.…

Read more »

golden sunset in crude oil refinery with pipeline system
Energy Stocks

Here’s How I’d Turn $14,000 in a TFSA Into $155 a Quarter

Canadians can easily turn their TFSA into a cash machine to receive recurring income streams.

Read more »

RRSP Canadian Registered Retirement Savings Plan concept
Energy Stocks

I Think This 1 TSX Stock Could Help You Catch Up on RRSP Savings

Enbridge (TSX:ENB) looks like a great buy-the-dip candidate for RRSP investors focused on growing wealth.

Read more »